Which two problems can be identified from the Program Board?

Prepare for the SAFe Version 5.1 Test with our comprehensive guide. Study with multiple-choice questions, flashcards, hints and explanations. Ace your exam!

The Program Board serves as an essential visual tool within the SAFe framework for tracking the progress of a program increment (PI). It displays features, milestones, team assignments, and dependencies between features and teams, facilitating transparency and communication within the Agile Release Train (ART).

Identifying too many dependencies leading to a single program milestone highlights a critical risk area. When multiple features depend on a single milestone, it can create a bottleneck, hindering the flow of value delivery. This saturation of dependencies can also lead to delays, increased complexity, and potential derailment of the overall PI objectives. By recognizing and addressing these dependencies on the Program Board, teams can proactively manage risks and ensure smoother execution of their work.

The other options, while they may reflect challenges encountered in agile practices, do not directly represent the type of problems that can be efficiently visualized through the Program Board in the context of feature progression and milestone achievement. Therefore, the identification of overlapping dependencies at a program milestone is particularly vital for maintaining a healthy flow of work and delivering value effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy