Which of the following statements is NOT correct?

Prepare for the SAFe Version 5.1 Test with our comprehensive guide. Study with multiple-choice questions, flashcards, hints and explanations. Ace your exam!

The assertion that integration points increase risk is not accurate in the context of the SAFe framework. Instead, integration points are designed to facilitate smoother collaboration and communication among teams, leading to a clearer understanding of project progress and any issues that may arise.

By implementing integration points, teams have structured opportunities to align their work, assess the performance of integrated components, and derive insights that enhance learning and adaptability. This approach tends to minimize uncertainty and risks associated with late-stage integrations, as it enables earlier detection of discrepancies and challenges.

As a result, while it might seem logical to associate integration points with an increase in risk, in practice, they serve to mitigate risk by promoting early testing and feedback loops, thereby accelerating overall learning and enhancing the quality of the product under development. Additionally, this understanding aligns with the principles of Lean-Agile methodologies, which emphasize continuous improvement and learning throughout the development process.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy