What does it indicate when a feature is placed in a team's swim lane with no strings on a Program Board?

Prepare for the SAFe Version 5.1 Test with our comprehensive guide. Study with multiple-choice questions, flashcards, hints and explanations. Ace your exam!

When a feature is placed in a team's swim lane on a Program Board without any strings attached to it, it clearly indicates that the feature can be completed independently from the efforts of other teams. This independence is crucial in Agile environments, as it allows teams to operate more efficiently, focusing on delivering value without being significantly affected by the progress or delays of other teams.

When features are not dependent on others, it not only simplifies the planning and execution process for the team but also enhances predictability in delivery timelines. Teams can prioritize this work based on their own capacity and commitments rather than having to wait for or coordinate with other teams, promoting a faster flow of value to the end customer.

The other options would suggest different scenarios that are either not indicated by the absence of strings or do not reflect the operational independence expressed by the placement of the feature on the board.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy